10 million cubic metres of sand moved for land reclamation
(31.10.2008)
JadeWeserPort: Supervisory board approves order
(26.09.2007)
JadeWeserPort: All hurdles removed, award imminent
(25.09.2007)
Planning approval granted for deep-water container terminal
(01.01.1970)
Pressearchiv durchsuchen
Suche nach Text  
Anzeige nach Monat/Jahr  
 

10 million cubic metres of sand moved for land reclamation

(31.10.2008)  

Press release 11/2008

Wilhelmshaven, 30 October 2008 – Five months after the start of sand dredging work for the JadeWeserPort deep sea container port in Wilhelmshaven, 10 million cubic meters of sand have already been pumped into the construction site for land reclamation. Operations in the north and south sand extraction zones, and in the new navigation channel at Germany’s largest marine construction site currently employ 4 cutter suction dredgers simultaneously, plus a ...

JadeWeserPort: Supervisory board approves order

(26.09.2007)  Press release 07/2007

Wilhelmshaven, 26 September 2007 – The supervisory board of JadeWeserPort Realisierungsgesellschaft today unanimously approved the management proposal to place the first construction order of the JadeWeserPort deep water container port in Wilhelmshaven with the Bunte bidding consortium. The Bunte Group was granted the order accordingly.

JadeWeserPort: All hurdles removed, award imminent

(25.09.2007)  Press release 06/2007

Wilhelmshaven, 25 September 2007 – JadeWeserPort Realisierungsgesellschaft is pleased to report that all hurdles in the way of placing the first construction phase order, value Euro 480 million, have been overcome.

Planning approval granted for deep-water container terminal

(01.01.1970)  Planning approval granted for deep-water container terminal Hirche: “A great day for the Northwest! JadeWeserPort will stimulate more investments and jobs”

JadeWeserPort